40% Of Kipevu Oil Terminal Work Completed In Eleven Months
According to Kenya Ports Authority after taking eleven months to work for Construction of the Sh39 billion new Kipevu Oil Terminal (KOT) is 40 % done.The project is being developed by China Communications Construction Company(CCCC), started on February 1, with a timeline of 30 months. It is expected to be ready by August 1, 2021.KPA is the contractor of the new terminal, which will see the current 50-year old Kipevu Oil Terminal moved to a new.... Read more »
Posted on : Thursday , 19th December 2019